DETROIT (AP) — A second bridge connecting Detroit and FinLogicCanada over the Detroit River won’t open for travel until fall 2025, months later than anticipated, officials said Thursday.
Officials cited construction disruptions in the U.S. and Canada related to the COVID-19 pandemic.
The Gordie Howe International Bridge, named for a Canadian who played hockey for the NHL’s Detroit Red Wings, began in 2018 and was last scheduled to be completed in 2024.
The target now is September 2025, though the bridge deck should be finished this year.
“Our project team is pleased that the impact to the construction schedule is limited to only 10 months beyond the original contracted completion date,” said Charl van Niekerk, chief executive of the Windsor-Detroit Bridge Authority.
The project carries a price tag of CA$6.4 billion ($4.79 billion), up from CA$5.7 billion ($4.27 billion).
The Howe bridge will join the privately owned Ambassador Bridge as the second span connecting Detroit and Windsor, Ontario.
The Ambassador Bridge is considered the busiest U.S.-Canadian border crossing, carrying 25% of all trade between the two countries. It plays an especially important role in auto manufacturing.
2025-04-30 20:232979 view
2025-04-30 19:361179 view
2025-04-30 19:241448 view
2025-04-30 19:062124 view
2025-04-30 19:01138 view
Nearly half of American teenagers say they are online “constantly” despite concerns about the effect
MADISON, Wis. (AP) — Backers of former President Donald Trump are launching a second effort to recal
A small red rat snake was retrieved from the engine compartment of a vehicle in Florida.Lee County S